Retro

demowho and where

Not a feature. Sign-in decides both of these; until then, this does.

Demo map
Operations

Retro

Iteration 3 — close the gaps · 18 Aug – 29 Aug · 5 of 16 days done · the line has not moved for 2 days

Same screen, other company —Mehta AutoSahyadri Systems

16 / 18

days committed of capacity

89% of capacity

5

days done

2 more in review, not counted

14

days per sprint, earned

average of closed sprints

2

days the line has not moved

Remaining days of effort, from the board

A rule the team set for itself has been broken

Book the founder's hour at planning, not at the end.” — Rohit owns it. EXP-12 is waiting on exactly that hour.

Iteration 2 — the gap list — retro, 15 Aug

Went well

  • · The gap list is honest — twelve gaps, all with a name.

Did not

  • · Two days lost because the auditor's checklist was in a PDF nobody could search.

Actions, and whether the next sprint kept them

  • Every requirement lives as a card with its evidence attached, not in the PDF.

    Shubhangikept
  • Book the founder's hour at planning, not at the end.

    EXP-12 is waiting on exactly that hour.

    Rohitbroken

Iteration 3 — close the gaps has not had its retro — it ends 29 Aug. The three questions will be here that day, and the actions will be checked in the sprint after.