Burndown
Iteration 3 — close the gaps · 18 Aug – 29 Aug · 5 of 16 days done · the line has not moved for 2 days
16 / 18
days committed of capacity
89% of capacity
5
days done
2 more in review, not counted
14
days per sprint, earned
average of closed sprints
2
days the line has not moved
Remaining days of effort, from the board
Iteration 3 — close the gaps — remaining days by day
From the board · the ideal line is straight from committed to zero · a blank is a day that has not happened
Remaining days of effort, from the board. Flat since Friday: EXP-8 is stuck finding heat numbers on paper, and EXP-12 is waiting on an hour of the founder's time.