Purchase requests
2 requests waiting · 3 orders open · 1 past the supplier’s promise · 1 bill held on the match
Updated 2026-08-26Raise a request
Purchase requests
3- EN8 bar stock, 32 mm · 3.2 tonnesorderedNilesh · 22 Aug · needed by 2 Sept
Q3 bracket schedule — Sharma's second lot and Sundaram's September
- CMM calibration, annual · 1 visitsapprovedShubhangi · 20 Aug · needed by 20 Sept
Annual CMM calibration due before the buyer audit in October · Approved by Vinod on the 21st; Prakash to raise the PO
This needs Prakash Kulkarni. - H-22 rough casting · 320 piecesrequestedNilesh · 25 Aug · needed by 8 Sept
Beta's housings — batch 7 is quarantined, so the balance needs fresh castings
Lead time is 21 days — ordered today it lands 16 Sept, after the date asked for. Say so before the PO, not after.