Purchase requests

demowho and where

Not a feature. Sign-in decides both of these; until then, this does.

Demo map
Operations

Purchase requests

2 requests waiting · 3 orders open · 1 past the supplier’s promise · 1 bill held on the match

Updated 2026-08-26Raise a request

Purchase requests

3
  • EN8 bar stock, 32 mm · 3.2 tonnesorderedNilesh · 22 Aug · needed by 2 Sept

    Q3 bracket schedule — Sharma's second lot and Sundaram's September

  • CMM calibration, annual · 1 visitsapprovedShubhangi · 20 Aug · needed by 20 Sept

    Annual CMM calibration due before the buyer audit in October · Approved by Vinod on the 21st; Prakash to raise the PO

    This needs Prakash Kulkarni.
  • H-22 rough casting · 320 piecesrequestedNilesh · 25 Aug · needed by 8 Sept

    Beta's housings — batch 7 is quarantined, so the balance needs fresh castings

    Lead time is 21 days — ordered today it lands 16 Sept, after the date asked for. Say so before the PO, not after.