engagement
Warehouse integration, phase two
$186,000For Northwind Logistics Inc. · Time and materials, billed monthly
Contracted in dollars because that is what the client signed. Corto never converts it: a rate needs a date, a date makes it an estimate, and Law 2 suppresses rather than estimates.
Promised 5 Oct 2026 · 35 days later than first given
31 Aug 2026 → 21 Sept 2026 · Nikhil Barve: “The client changed the warehouse mapping after the build had started. Their change, our date.” · told Rahul Menon, Anjali Rane
21 Sept 2026 → 5 Oct 2026 · Nikhil Barve: “Kartik was on the Vaayu pilot for three weeks. Ours, not theirs.” · told Rahul Menon, Anjali Rane
Nikhil Barve owns it · Rahul Menon is the one who reaches the customer if the date moves · Kartik Bhave · Lead engineer · Omkar Pawar · QA
engagement
Store rollout, 40 outlets
₹42,00,000For Vaayu Retail Pvt Ltd · Fixed fee, three milestones
Promised 31 Oct 2026 · never moved
Pilot, four outlets1 of 1 deliverablesticked · 0 deliverables counted
Handed over on 2 August. The client has still not signed the acceptance note, so it is delivered and not accepted — which is where the money sits.
Rollout, 36 outlets11 of 36 deliverables
Handover and training0 of 1 deliverables
Two meanings of done
Delivery says done when the work was handed over. The client says done when they accepted it. They are 1 deliverables apart. The gap between the two is where a services company's money actually sits.
Nikhil Barve owns it · Rahul Menon is the one who reaches the customer if the date moves · Kartik Bhave · Rollout lead
sprint
Sprint 31 — route planning
For Sahyadri Systems itself — nobody outside is waiting on it · Two weeks, the team's own commitment
A sprint has no invoice, and putting a rupee figure on one would be an estimate with a person's salary inside it. The field is empty on purpose.
Promised 4 Sept 2026 · never moved
SPR-2 · Save a planned route8 of 8 pointsshipped
SPR-3 · Reorder stops by drag5 of 5 pointsshipped
SPR-4 · Share a route with a driver13 of 13 pointsticked · 0 points counted
Farhan ticked it when the code was complete. It is not behind the flag for any customer yet, so Sneha has not counted it. Both are true and neither is wrong.
SPR-7 · Print a route sheet0 of 8 points
Not started. It was pulled in at planning over Omkar's objection that there was no test data for it.
Two meanings of done
Engineering says done when the code is complete. Product says done when customers have it. They are 13 points apart. The same disagreement as a factory's line and its gate, and it costs the same thing: a promise that reads as kept while nobody outside has received anything.
Farhan Qureshi owns it · Sneha Vaidya is the one who reaches the team if the date moves · Ritika Sen · Engineer · Omkar Pawar · QA