15 Jul to 10 Oct
Every project as a bar, every milestone as a mark, today as the line. A milestone left of the line with no tick is late — the bar says nothing the milestones do not.
Export audit — IATF and customer pack · Shubhangi
Procedure pack 5 Sept · Calibration register clean 20 Sept · Internal audit and closure of findings 1 Oct · Audit day 10 Oct
H-22 second line — commissioning · Vinod
Machines delivered and levelled 10 Aug ✓ · Fixtures and first-off approved by quality 30 Aug · Operators trained, two shifts 20 Sept · First full week at rate 30 Sept
Corto rollout — the parallel tracks · Meera
Everyone joined 20 Aug ✓ · Every head has agreed their objectives 31 Aug · Every goal accepted 15 Sept · First real use, per person 30 Sept