3 projects · 1 at risk · progress is counted from what is done, never typed

Updated 2026-08-26Start a project

Export audit — IATF and customer pack

6

Shubhangi · due 10 Oct · 2 of 6 done. A milestone is done when its tasks are.

Procedure pack — twelve procedures writtendue 5 SeptSwapnil

  • QP-01 to QP-08 written and reviewedSwapnil · 25 Aug · done
  • QP-07 calibration control — one version, not twoShubhangi · 23 Aug · done
  • QP-09 to QP-12 — the last fourSwapnil · 3 Sept · in progress

Calibration register clean — gauges and CMMdue 20 SeptShubhangi

  • CMM calibration visit booked (PR-2 → PO)Prakash · 1 Sept · not started
  • Replace the scrapped thread gaugeShubhangi · 10 Sept · not started

Internal audit and closure of findingsdue 1 OctShubhangi

  • Internal audit — two days, Omkar leadsOmkar · 26 Sept · not started

Audit daydue 10 OctShubhangi

  • no tasks yet

H-22 second line — commissioning

4

Vinod · due 30 Sept · 2 of 4 done. A milestone is done when its tasks are.

Machines delivered and levelleddone 12 AugVinod

  • Foundation and powerDilip · 5 Aug · done

Fixtures and first-off approved by qualitydue 30 AugKiran

  • Fixture drawings releasedKiran · 18 Aug · done
  • First-off inspection — waiting on castings from batch 8Shubhangi · 28 Aug · in progress

Operators trained, two shiftsdue 20 SeptGanesh

  • Training plan and rosterGanesh · 5 Sept · not started

First full week at ratedue 30 SeptVinod

  • no tasks yet

Corto rollout — the parallel tracks

3

Meera · due 30 Sept · 0 of 3 done. A milestone is done when its tasks are.

Everyone joineddone 19 AugMeera

  • no tasks yet

Every head has agreed their objectivesdue 31 AugMeera

  • Vinod's capacity objective — returned, resubmitVinod · 28 Aug · in progress

Every goal accepteddue 15 SeptMeera

  • Datta's goal — the gate-out clauseSuresh · 29 Aug · not started

First real use, per persondue 30 SeptMeera

  • Migration date per module — CRM firstMeera · 8 Sept · not started