Backlog
Sprint 31 — route planning · 24 Aug – 4 Sept · 13 of 37 points done · 3 points over capacity · the line has not moved for 2 days
37 / 34
points committed of capacity
3 over — already late on day one
13
points done
13 more in review, not counted
27
points per sprint, earned
average of closed sprints
2
days the line has not moved
Remaining points by day, from the board
Backlog
5- SPR-11Route ETA from live trafficstory
unassigned · Needs a maps provider decision. Too big for one sprint as written.
21 points - SPR-9Driver app: offline route cachestory
unassigned · Asked for by the Indore distributor on LinkedIn. Not estimated by the team yet — the 13 is Sneha's guess.
13 points - SPR-14Beta sign-up form → Corto's one doortask
unassigned
5 points - SPR-10Pricing page copy behind the flagtask
unassigned
3 points - SPR-13Analytics event on route sharedtask
Omkar
2 points
Sprint 30 — stops and drivers
closedA dispatcher can add stops and assign a driver
10 Aug – 21 Aug · 0 of 34 points · 27 done
Sprint 31 — route planning
activeA dispatcher can plan a route and share it with a driver
24 Aug – 4 Sept · 37 of 34 points
Sprint 32 — the launch week
plannedEverything the launch email promises is behind the flag
7 Sept – 18 Sept · 0 of 30 points