Retro
Sprint 31 — route planning · 24 Aug – 4 Sept · 13 of 37 points done · 3 points over capacity · the line has not moved for 2 days
37 / 34
points committed of capacity
3 over — already late on day one
13
points done
13 more in review, not counted
27
points per sprint, earned
average of closed sprints
2
days the line has not moved
Remaining points by day, from the board
A rule the team set for itself has been broken
“No story enters a sprint without test data.” — Omkar owns it. SPR-7 was pulled into 31 without it, over Omkar's objection. The retro rule the team set for itself was broken by the team a week later, and the board shows the cost.
Sprint 30 — stops and drivers — retro, 21 Aug
Went well
- · Stops and drivers shipped behind the flag on day 9.
- · Omkar's device matrix caught the Android 12 drop before a customer did.
Did not
- · Three items pulled in mid-sprint from the Vaayu rollout.
- · Nobody owned the release notes; they went out a day late.
Actions, and whether the next sprint kept them
Nothing enters a sprint after day 2 without Farhan and Sneha both agreeing.
Held in sprint 31 — the Vaayu request went to the backlog.
FarhankeptRelease notes are a story on the board, owned, with points.
SnehakeptNo story enters a sprint without test data.
SPR-7 was pulled into 31 without it, over Omkar's objection. The retro rule the team set for itself was broken by the team a week later, and the board shows the cost.
Omkarbroken
Sprint 31 — route planning has not had its retro — it ends 4 Sept. The three questions will be here that day, and the actions will be checked in the sprint after.