Retro

Sprint 31 — route planning · 24 Aug – 4 Sept · 13 of 37 points done · 3 points over capacity · the line has not moved for 2 days

Same screen, other company —Mehta AutoSahyadri Systems

37 / 34

points committed of capacity

3 over — already late on day one

13

points done

13 more in review, not counted

27

points per sprint, earned

average of closed sprints

2

days the line has not moved

Remaining points by day, from the board

A rule the team set for itself has been broken

No story enters a sprint without test data.” — Omkar owns it. SPR-7 was pulled into 31 without it, over Omkar's objection. The retro rule the team set for itself was broken by the team a week later, and the board shows the cost.

Sprint 30 — stops and drivers — retro, 21 Aug

Went well

  • · Stops and drivers shipped behind the flag on day 9.
  • · Omkar's device matrix caught the Android 12 drop before a customer did.

Did not

  • · Three items pulled in mid-sprint from the Vaayu rollout.
  • · Nobody owned the release notes; they went out a day late.

Actions, and whether the next sprint kept them

  • Nothing enters a sprint after day 2 without Farhan and Sneha both agreeing.

    Held in sprint 31 — the Vaayu request went to the backlog.

    Farhankept
  • Release notes are a story on the board, owned, with points.

    Snehakept
  • No story enters a sprint without test data.

    SPR-7 was pulled into 31 without it, over Omkar's objection. The retro rule the team set for itself was broken by the team a week later, and the board shows the cost.

    Omkarbroken

Sprint 31 — route planning has not had its retro — it ends 4 Sept. The three questions will be here that day, and the actions will be checked in the sprint after.