Burndown

demowho and where

Not a feature. Sign-in decides both of these; until then, this does.

Demo map
Operations

Burndown

Sprint 31 — route planning · 24 Aug – 4 Sept · 13 of 37 points done · 3 points over capacity · the line has not moved for 2 days

Same screen, other company —Mehta AutoSahyadri Systems

37 / 34

points committed of capacity

3 over — already late on day one

13

points done

13 more in review, not counted

27

points per sprint, earned

average of closed sprints

2

days the line has not moved

Remaining points by day, from the board

Sprint 31 — route planning — remaining points by day

From the board · the ideal line is straight from committed to zero · a blank is a day that has not happened

Remaining points by day, from the board. The flat line from 28 August is SPR-4 sitting in review — thirteen points that will not burn until product counts them.