Sprint board

demowho and where

Not a feature. Sign-in decides both of these; until then, this does.

Demo map
Operations

Sprint board

Iteration 3 — close the gaps · 18 Aug – 29 Aug · 5 of 16 days done · the line has not moved for 2 days

Same screen, other company —Mehta AutoSahyadri Systems

16 / 18

days committed of capacity

89% of capacity

5

days done

2 more in review, not counted

14

days per sprint, earned

average of closed sprints

2

days the line has not moved

Remaining days of effort, from the board

Iteration 3 — close the gaps

Goal: Eight of the twelve gaps closed with evidence a buyer's auditor would accept

To do2 · 5 days
  • EXP-114 days

    Internal audit of the new line, with findings closed

    Shubhangi

  • EXP-121 days

    Management review minutes, signed

    Rohit

    Needs an hour of Anil's time that nobody has booked.

In progress1 · 4 days
  • EXP-84 days

    Traceability from heat number to dispatch, one lot end to end

    Shubhangi

    The heat numbers are on paper in stores. Two days went to finding them.

In review1 · 2 days
  • EXP-92 days

    Written procedure for customer complaints

    Rohit

    Drafted by Rohit; Shubhangi has not signed it off. Done by one meaning, not the other.

Done2 · 5 days
  • EXP-62 days

    Calibration records for the CMM, last 12 months

    Shubhangi · done 20 Aug

  • EXP-73 days

    Supplier approval list with dates

    Swapnil · done 22 Aug