Sprint 31 — route planning · 24 Aug – 4 Sept · 13 of 37 points done · 3 points over capacity · the line has not moved for 2 days

Same screen, other company —Mehta AutoSahyadri Systems

37 / 34

points committed of capacity

3 over — already late on day one

13

points done

13 more in review, not counted

27

points per sprint, earned

average of closed sprints

2

days the line has not moved

Remaining points by day, from the board

Sprint 31 — route planning

Goal: A dispatcher can plan a route and share it with a driver

To do1 · 8 points
  • SPR-78 points

    Print a route sheet

    Omkar

    No test data for a printed sheet — Omkar said so at planning and it was pulled in anyway.

In progress1 · 3 points
  • SPR-123 points

    Fix: stop reorder loses the last stop on slow networks

    Ritika

In review1 · 13 points
  • SPR-413 points

    Share a route with a driver

    Ritika

    Code complete 30 Aug. Not behind the flag for any customer yet, so product has not counted it.

Done2 · 13 points
  • SPR-28 points

    Save a planned route

    Ritika · done 27 Aug

  • SPR-35 points

    Reorder stops by drag

    Ritika · done 28 Aug