Operations
Purchase orders
2 requests waiting · 3 orders open · 1 past the supplier’s promise · 1 bill held on the match
Updated 2026-08-26Raise a request
Purchase orders
3Every order, its promise and what has arrived against it. Open one for the moves, the receipts and the bills.
| MA/PO/26-27/1188 | Kalyani Steel Supply | 3.2 tonnes EN8 bar stock, 32 mm | 841600 | 14 Aug 2026 · moved once, +9 days | 3.2 of 3.2 | received | Prakash |
| MA/PO/26-27/1189 | Kalyani Steel Supply | 3.2 tonnes EN8 bar stock, 32 mm | 841600 | 31 Aug 2026 | 0 of 3.2 | open | Prakash |
| MA/PO/26-27/1190 | Pune Precision Foundry | 300 pieces H-22 rough casting | 243000 | 21 Aug 2026 · moved once, +3 days | 300 of 300 · 12 rejected | 5 days late | Prakash |
| 3 orders | ₹19,26,200 |