Purchase order
MA/PO/26-27/1188
Kalyani Steel Supply · 3.2 tonnes EN8 bar stock, 32 mm
- receiptEN8 bar stock, 32 mm · Heat 4471-A14 Aug 2026
Nine days after the original promise. The Sharma second lot moved because of it.
3.2 tonnes received by Suresh, 3.2 accepted by Shubhangi · all accepted
- billKSS/2026/1188 · ₹8,42,0004 Aug 2026
PO 3.2 t · received 3.2 t · billed 3.2 t. Three-way match holds; ₹8,42,000 is 3.2 × ₹2,63,000 plus GST.
Kalyani Steel Supply · matched
- promise moved5 Aug 2026 → 14 Aug 20263 Aug 2026
Mill delay — the supplier's own supplier; told us on the 3rd, not the 5th
told 3 Aug 2026 · told before the date