3 projects · 1 at risk · progress is counted from what is done, never typed

Updated 2026-08-26Start a project

Export audit — IATF and customer pack

6

Shubhangi · due 10 Oct · 2 of 6 done. A milestone is done when its tasks are.

Procedure pack — twelve procedures writtendue 5 SeptSwapnil

  • QP-01 to QP-08 written and reviewedSwapnil · 25 Aug · done
  • QP-07 calibration control — one version, not twoShubhangi · 23 Aug · done
  • QP-09 to QP-12 — the last fourSwapnil · 3 Sept · in progress

Calibration register clean — gauges and CMMdue 20 SeptShubhangi

  • CMM calibration visit booked (PR-2 → PO)Prakash · 1 Sept · not started
  • Replace the scrapped thread gaugeShubhangi · 10 Sept · not started

Internal audit and closure of findingsdue 1 OctShubhangi

  • Internal audit — two days, Omkar leadsOmkar · 26 Sept · not started

Audit daydue 10 OctShubhangi

  • no tasks yet