H-22 second line — commissioning
4Vinod · due 30 Sept · 2 of 4 done. A milestone is done when its tasks are.
Machines delivered and levelleddone 12 AugVinod
- Foundation and powerDilip · 5 Aug · done
Fixtures and first-off approved by qualitydue 30 AugKiran
- Fixture drawings releasedKiran · 18 Aug · done
- First-off inspection — waiting on castings from batch 8Shubhangi · 28 Aug · in progress
Operators trained, two shiftsdue 20 SeptGanesh
- Training plan and rosterGanesh · 5 Sept · not started
First full week at ratedue 30 SeptVinod
- no tasks yet